Which of the following statements is TRUE about the procedure after detention of shipments under the Toxic Substances Control Act (TSCA) of a covered commodity?

  1. The importer of the detained shipment must bring the shipment into compliance with Toxic Substances Control Act or export the shipment from the customs territory of the United States within 90 days after notice of detention or 30 days of demand for redelivery, whichever comes first.
  2. The importer of the detained shipment must submit written documentation to the Administrator with a copy to the port director within 90 days from the date of notice of detention, to show why the shipment should not be refused entry.
  3. The importer of the detained shipment must bring the shipment into compliance with Toxic Substances Control Act or export the shipment from the customs territory of the United States within 120 days after notice of detention or 60 days of demand for redelivery, whichever comes first.
  4. The importer of the detained shipment must submit written documentation to the Administrator with a copy to the port director within 120 days from the date of notice of detention, to show why the shipment should not be refused entry.
Show the answer and walk-through

CBP's answer: A. A: The importer of the detained shipment must bring the shipment into compliance with Toxic Substances Control Act or export the shipment from the customs territory of the United States within 90 days after notice of detention or 30 days of demand for redelivery, whichever comes first.

For a detained TSCA covered commodity, the importer must bring the shipment into compliance or export it within 90 days after notice of detention or 30 days of demand for redelivery, whichever comes first (12.124(a)). That is A. The 120 and 60 day figures in C are wrong, and the written-documentation choices are not what this paragraph requires.

must bring the shipment into compliance with TSCA or export the shipment from the customs territory of the United States within 90 days after notice of detention or 30 days of demand for redelivery, whichever comes first 19 CFR 12.124(a)

Search for: within 90 days after notice of detention or 30 days of demand for redelivery

CBP's key cites: 19 CFR 12.124(a)

Question and key from CBP's April 2026 exam and answer key. The walk-through is ours; quotes are from the pinned editions in the reference viewer (HTSUS 2026 Basic, 19 CFR 2025 edition).